What Is The Average Time To Finish A Basement?

What Is The Average Time To Finish A Basement

article

What Is The Average Time To Finish A Basement

What is the time frame for completing a basement? Learn more about the typical basement finishing timeline and which phases take the longest.

 

There are numerous factors to consider when determining how long it takes to finish a basement. The first thing you should do is find a contractor. A contractor can assist you in determining the most accurate timeline for your finished basement project. A custom-finished basement project lasts between 12 and 16 weeks, and the timeline may reflect your specific basement renovation plans.

 

How Are Basement Finishing Timelines Scheduled?

So, you met with a contractor and developed a plan and proposal; now comes the exciting part! The basement transformation begins once the pre-work completes and the basement is ready.

 

  • One day to deliver rough materials
  • Framing: This can take anywhere from 5-7 days to complete.
  • Electrical and can complete rough plumbing in 5-7 days.
  • 3-5 days for rough inspections
  • One day to install insulation
  • Putting up a sign 10-14 days for drywall
  • Finishing and priming 2-3 days for drywall
  • Delivery time for doors and trim: one day
  • Trim installation time: 5-7 days
  • 1-4 days to set up cabinets
  • 2-4 days for the ceiling grid
  • Two days for spotting
  • 2-4 days for the first painting
  • Tile installation takes 2-4 days.
  • One day to install countertops
  • 4-6 days for flooring installation
  • Mechanical completion: 2-3 days
  • Second sighting: 2 to 5 days
  • 2-4 days for the second painting
  • Two days for carpet installation
  • 2-5 days for final touch-ups
  • 2-5 days for final inspections
  • Three days for punchout
  • One day for final cleaning

 

Is There Anything That Could Lead To A Timeline Extension?

Although there is a general timeline for basement finishing, life happens, and delays can occur. If you have a larger space, framing it may take longer than the 5-7 days allotted. Any plumbing or electrical issues that arise can also cause a delay. Another factor to consider is inspections. Inspections take one day, but the inspector may take several days to arrive at the job site. The larger the basement, the longer the project will take, but contractors can usually give you a very accurate estimate.

 

The Advantages Of Professional Basement Finishing

There are numerous advantages to having a professionally finished basement. Should you hire a pro or do it yourself for your Basement Finishing Project? Basement remodeling professionals and contractors have a clear vision and understand what to expect. They are aware of potential setbacks and prepare to deal with any delays. When a professional gives you a timeline, you should expect the work to closely follow it.

 

Allow Us To Assist You In Defining Your Basement Finishing Timeline

A completed basement timeline can put your mind at ease. ASASA Construction can assist you in bringing your vision to life in a timely and professional manner. Contact us today for a no-obligation consultation. Please contact ASASA Construction now.

WE ARE THE MOST TRUSTED AND EXPERIENCED COMMERCIAL AND RESIDENTIAL CONTRACTOR IN TORONTO.

GET THE BEST EXPERTS FOR YOUR CONSTRUCTION AND RENOVATION PROJECTS.

Read Testimonials

We Always Love To Hear From Our Customers